TCN Inspects Katsina Substation Ahead of Major Installation

THISDAYLIVE | 29-09-2026 08:37pm |

The Transmission Company of Nigeria (TCN), Katsina Sub-Region, and Imcomtel Engineering Limited inspected the Katsina 330/132/33kV Transmission Substation ahead of the next major phase of equipment installation. The inspection was led by Assistant General Manager (Transmission) Usman Idris, who received the Imcomtel delegation headed by Emmanuel Okafor. The team assessed ongoing civil works, equipment locations, and supporting infrastructure to determine readiness for the next stage. A key focus was the site designated for two 100MVA power transformers delivered on July 9, 2026. Once installed and commissioned, the transformers are expected to significantly increase transmission capacity in Katsina State and strengthen electricity delivery across the North-West region.